Show cause issued on Upper Karnali deal
The Supreme Court on Friday issued a show cause notice to the government regarding the latter's agreement with India's GMR Energy Ltd on the 300 MW Upper Karnali Hydroelectric Project.
Besides, the Supreme Court said that it would hold a discussion on March 7 on whether the implementation of the agreement should be stayed, as demanded by writ petitioners Gorakh Bahadur B.C of Kalikot and Ram Singh Rawal of Surkhet, while summoning the defendants to be present before it on that day.
B.C. and Rawal moved the court with a Public Interest litigation (PIL), accusing the government of violating Article 156 (1) (2) (D) and (3) of the Interim Constitution while awarding the project to GMR early this year.
They argued that the constitutional provisions require an approval from a two-third majority of the lawmakers in the parliament prior to inking any agreement on natural resources, but the Upper Karnali agreement was signed without meeting the constitutional requirements.
Justice Balram KC passed the order after an initial hearing on Friday.
Office of the Prime Minister, Ministry of Water Resources, Ministry of Environment, Science and Technology, Ministry of Finance, Parliamentary Committee on Natural Resources and Means, Parliamentary Finance Committee and Department of Electricity Development have been made defendants in the case.
The Supreme Court on Friday issued a show cause notice to the government regarding the latter's agreement with India's GMR Energy Ltd on the 300 MW Upper Karnali Hydroelectric Project.
Besides, the Supreme Court said that it would hold a discussion on March 7 on whether the implementation of the agreement should be stayed, as demanded by writ petitioners Gorakh Bahadur B.C of Kalikot and Ram Singh Rawal of Surkhet, while summoning the defendants to be present before it on that day.
B.C. and Rawal moved the court with a Public Interest litigation (PIL), accusing the government of violating Article 156 (1) (2) (D) and (3) of the Interim Constitution while awarding the project to GMR early this year.
They argued that the constitutional provisions require an approval from a two-third majority of the lawmakers in the parliament prior to inking any agreement on natural resources, but the Upper Karnali agreement was signed without meeting the constitutional requirements.
Justice Balram KC passed the order after an initial hearing on Friday.
Office of the Prime Minister, Ministry of Water Resources, Ministry of Environment, Science and Technology, Ministry of Finance, Parliamentary Committee on Natural Resources and Means, Parliamentary Finance Committee and Department of Electricity Development have been made defendants in the case.